ElectricalSlab Underground
Rough-InTo be made after the roof, framing, fire-blocking and bracing is in place and prior to the installation of wall membranes. Electrical Test PowerThe following are some of the items inspectors will be checking before final inspection can be final:
MechanicalUnderground InspectionTo be made after trenches or ditches are excavated, underground duct and fuel piping installed, and before any backfill is put in place.
Rough-InTo be made after the roof, framing, fire-blocking and bracing is in place and all ducting and other concealed components are complete, and prior to the installation of insulation and wall or ceiling membranes. Second Rough-InTo be performed prior to the installation of walls or ceiling membranes and after the roof, framing, fire-blocking and bracing is in place and all drainage, waste, vent, and water distribution piping is complete. PlumbingUnderground InspectionTo be made after trenches or ditches are excavated, piping is installed and tested, and before any backfill is put in place.
Rough-InTo be made after the roof, framing, fire-blocking and bracing is in place and all gas, water, soil, waste and vent piping is complete and tested, and prior to the installation of insulation and wall or ceiling membranes. Final: To be made after the building is complete, the mechanical system is in place and properly connected, and the structure is ready for occupancy. For further information, please refer to Inspection Requirements and Codes.
|