Any inspection requiring a specific time or date for either testing or walk through
must be scheduled with the inspector. Calling on the computer line does not guarantee a
next day inspection by the Fire Inspector.
NOTE: All permits require at least a final inspection.
Fire Alarm Inspection
All appliances must be installed and pre-tested by certified contractor.
Artificial smoke, magnets, ladders, radios, etc. ... must be provided for proper testing
of equipment.
Approved plans and Certification papers must be on site.
Fire Protection Inspection
If underground is installed, hydrostatic testing with exposed piping is required. Have
approved plans and certification papers on site.
New overhead installations require hydrostatic testing.
Any relocation or additional of existing heads requires a permit.
Fire Suppression Inspection
Functional test is required for final approval.
Gas/electric must be turned on.
Coordination with fire alarm contractor is required if fire alarm is a part of project
or existing.
Final Inspection
All life safety features must be in place and functional.
If applicable, fire alarm, fire protection and fire suppression must have been
previously tested and approved.
Fire walls are exposed, marked and penetrations properly sealed with fire rated
caulking.