Quick Links
|
Bonfire/Campfire/Open Burning Permits
Effective date: October 2, 1997
 
When completing a permit for either a bonfire or a campfire the following
information is required:
-
Date and time it is scheduled to start and be finished (30 day
maximum)
-
Site Plan
-
Copy of warranty deed for property
-
Letter from the owner of the property giving permission for the bon
fire/campfire to be held and naming the responsible adult in charge
-
Purpose of the event
-
EPA approval required, in writing (Phone 813-272-5530)
The following information must be written on the
permit.
-
Only ordinary combustibles can be burned, no garbage, chemical,
hazardous materials or flammables.
-
Fire must be extinguished when the event is completed.
-
This permit may be revoked:
Due to inclement weather conditions
or Complaints are received from the neighbors
The fee of $25.00 must be collected and the permit must be
approved before the event can be held.