Tampa Trails & Greenways Project Minutes of Advisory Committee Meeting
|
Call to Order
|
Date: April 13, 2004
|
-
The meeting was called to order at approximately 2:40pm
|
Attendees:
|
- Sally Thompson, Chair; Randy Stribling,
South Seminole Heights Neighborhood Association; Mary Helen
Duke, Greenways & Trails Coordinator.
|
|
|
- Ms. Duke announced that the meeting had
received proper public notice in the City Clerk’s office and
called the meeting to order. She handed out draft CMAQ
applications for six proposed projects and explained that four
of these projects had been submitted in previous years, yet
remained unfounded by either the MPO or FDOT7. She noted that
the purpose of the meeting was to review each proposed project
based on the segment prioritization evaluation matrix adopted as
part of the Tampa Greenways and Trails Master Plan by City
Council in February 2001. Ms. Duke handed out score sheets based
on evaluation matrix. After discussion, the subcommittee decided
to use one score sheet for all six projects. The six projects
under consideration included:
* Hillsborough River Greenway- Pedestrian Bridge Connector;
* Hillsborough River Greenway – Downtown Phase; * Hillsborough River Greenway – Lowry Park Phase;
* South Tampa Greenway; * Lemon Street/Cypress Point Park Connector; and
* Bayshore Boulevard Greenway - South Davis Boulevard
Multi-Purpose Path.
The subcommittee discussed each of the six criteria for each
project and developed project rankings within each criteria for
the first ten criteria listed on the score sheet. See attached.
Ms Duke was authorized to complete the score sheet on behalf of
the subcommittee. Another meeting would be scheduled for the
subcommittee to review the staff recommendations.
At approximately 5:05pm, the meeting adjourned
|
|
|
 |