Sally Thompson, Chair, called the meeting to order at 6:30pm.
A. Introductions - Chair Thompson requested attendees to
provide self-introductions.
B. Minutes of November 9, 2004 – Duke reported minutes were
not ready for review.
C. Public Comments - Chair Thompson opened the floor to public
comment. There was none.
Presentations
D. Gandy/Bridge Street - Duke provided a status report on the
Gandy Boulevard Underpass CMAQ application. She explained FDOT did
not support the underpass concept and has instructed the City to
submit an application for a pedestrian crossing study to determine
the best location for a pedestrian crossing of Gandy Boulevard to
link the Friendship Trail Bridge to the South Tampa Greenway. Duke
introduced Don Gunn and Bill Hoyt of Eco Group, developers of the
project along Bridge Street. The project includes a portion of the
South Tampa Greenway Trail. Chair Thompson asked them to speak.
They declined comment. Discussion was postponed to the March 9
meeting date.
E. LaSalle Open Space Linear Park/Links II/III – Duke
referred to the handout concept drawing for the LaSalle Open Space
Linear Park developed by the FDOT consultant, Jonathan Toner for
the project. This park will have a trail and run between Armenia
Avenue and Howard Avenue and should be completed in 2012. Jane
Burmer asked about the designation of types of uses and noted that
roller blading is not good on brick. Sally Thompson noted it might
be better if edged with brick. Sally Thompson asked about public
participation and awareness of the project. Duke stated FDOT has
conducted several meetings with the neighborhoods and Westshore
Alliance. The City will probably enter into a maintenance
agreement with FDOT for the linear park. Dan Thornburgh suggested
using the Pinellas Trail as a model. The majority of the trail has
blacktop, not bricks and some crosswalks. He suggested contacting
Gary Gumbee, the design engineer.
Old Business
F. Project Updates
- Hillsborough River Greenway
- Blake Trail (landscape plantings 1/17/05) Karla Price
provided a status report on construction of the Blake Trail.
An easement agreement is in the works with Tampa Prep. This
is for the Boardwalk portion. A feasibility study is needed
and will be included in the FY06 City budget. Landscape
plantings were initiated on Monday. Denny Atrem of the
Steward Foundation has worked with the City on the Blake
Trail. Price reported there are School Board concerns. We
continue to work with the University of Tampa that leases
Plant Park from the City.
- Rivercrest Park Trail – Price reported that asphalt is
scheduled to be laid this week. Work is progressing.
- Tampa Heights Greenway – Duke reported a concept
landscape plan has been prepared by FDOT’s landscape
architect (provided in packet). The concept plan will need
to be reviewed by the ARC.
- Riverwalk – Duke provided an update on the Riverwalk
project. The Bank of America property development may include
an extension of about 1 mile of Riverwalk. Lee Hoffman will be
invited to the next meeting to provide a status report. Sharon
Keene suggested staff contact Bill Bishop, developer of the
project. A meeting with the neighborhood will be held at
Stetson on February 3. Sharon Keene asked if North Boulevard
could be 3 laned?
- South Tampa Greenway
- MacDill Trail – Gadsden Park – Duke reported that
another 200 trees have been planted by the Mayor’s
Beautification Program and that signs have been ordered.
- Manhattan Avenue Trail Connection (ROW Certification) –
Duke reported that an application is being prepared for TIP
TE funding for missing segments of the South Tampa Greenway
between the Friendship Trail Bridge and Bayshore Boulevard.
- Gandy Boulevard Underpass (Pedestrian Access Study &
NEPA) - See above discussion.
- South Tampa Greenway Master Management Plan (Trailhead)
Keen parcel Concept Plan Development - Duke presented the
concept land management plan to the group. Tom Ries of
Scheda Environmental was present to ask questions.
Discussion on the concept plan followed.
- McKay Bay Greenway
- I-4 Connector/McKay Bay Nature Park – Duke reported that
the City was in ongoing mediation sessions with FDOT and
THEA regarding the impact of the I-4 Connector project to
McKay Bay Nature Park and the McKay Bay Greenway. City staff
is working to get the trail constructed as part of the
project.
- West Tampa Greenway
- Westshore Pedestrian Plan & Westshore District Overlay
Zone - Duke reported that MPO and City staffs are working on
these two studies. CAC members were encouraged to contact
Duke for more information and drafts of the documents.
- Development Review Report – Duke stated that development
review activity was high and commitments were being secured
for trail construction.
New Business
G. Tampa Greenways & Trails Master Plan Map Amendment
Process, Schedule & Presentation of Proposed Map Amendments -CAC
Procedure, Rules & Bylaws - Duke presented a draft set of CAC
Procedures, Rules and Bylaws for CAC review and discussion.
Discussion followed on membership makeup, greenway area
representation, etc. Dan Thornburgh asked about newspaper notice.
Duke replied all meetings are noticed on the City website, as well
as in the City Clerk’s office. CAC members were encouraged to
thoroughly review the draft and provide comments back to staff
prior to the next meeting. A subcommittee was formed to further
evaluate in detail the draft with staff.
H. Other Business/Announcements
- MPO Walkable Communities Workshops, April 4 – 8 - Duke
referred to the handout of the workshop schedule and
encouraged CAC members to attend.
- Pro Walk/ProBike Conference, April 5 – 8 – Duke informed
the CAC of this training opportunity and encouraged attendance
by interested members.
- Gasparilla Children’s Parade Bicycle Rodeo – Duke
encouraged anyone interested in volunteering to contact the
MPO.
- Sunshine Law – Duke provided this information to the CAC
members for information.
I. CAC 2005 Meeting Schedule - Duke presented a draft schedule
for 2005 meetings. The March 15th date was changed to
March 29th. A motion was made by Sharon Keene to
approve the schedule as revised, and seconded by Stan Kroh. The
motion was approved.
J. Next Meeting Date: Tuesday March 15, 2006. Chair Thompson
announced the next meeting at Kate Jackson Community Center.
K. Adjourn – Chair Thompson adjourned the meeting.
Respectfully Submitted:
Mary Helen Duke
Greenways & Trails Coordinator
Approved:
|