4. Tampa Bay History Center with Sidewalk to Channelside Drive
  Riverwalk image  
Project Report as of October, 2007
Length 1,140'
Status The City is working with County Project Manager to build this Riverwalk segment in conjunction with the new Tampa Bay History Center.  The pathway to Channelside Drive will include a plaza and gateway entry to the Riverwalk at the corner of Beneficial and Channelside Drive.  Design of this segment is underway.  Construction of the History Center Building began in October, 2007 and will be complete in late 2008.  Construction of the Riverwalk segment will begin in the Summer of 2008 and be complete in late 2008.
Priority High