Flood Relief - Coachman/Alline/Asbury Ave |
Project ID:
11-09
Fiscal Year:
2011
Project Address:
2921 W Alline Ave, 33611
|
Estimated Project Cost $5,000,000
|
Description This low-lying basin is subject to flooding during high tides. A back-flow prevention device was installed to reduce saltwater flooding but this has increased the propensity for freshwater flooding during extreme rainfall events.
This project will consist of the installation of a pumping system to assist the gravity system in removing floodwaters from the basin.
|
|
|
|