To serve its reclaimed water customers more efficiently, Volt Telecom Group, Inc. a contractor for the Tampa Water Department, will be flushing Tampa's reclaimed water as part of a preventive maintenance project designed to enhance the overall operation of Tampa's reclaimed water system and support the City’s focus on improving neighborhoods.
 



Transmission Main Flushing:

Flushing of the transmission main is scheduled to begin October 19, 2009, and should be completed no later than October 25, 2009. All customers should expect an interruption of their reclaimed water service throughout this period and plan accordingly for their irrigation needs. Because we will be using high levels of chlorine to flush the transmission system, it is crucial that customers do not turn their reclaimed water meter back on, or use any reclaimed water on their property, until notified it is safe to do so once the system has been shut down by the contractor.    


 

Distribution Line Flushing:

Between mid-November and mid-March each of the five reclaimed water distribution system zones are also scheduled to be flushed, resulting in short periods of service interruptions. Customers in each zone will be sent letters from the Tampa Water Department approximately two weeks prior to the flushing activity scheduled to effect their service.

Zone Map

Zone Map (1163 KB, PDF)

Projected Schedule of Distribution Flushing Activity By Zone:

Zone E: 11/30/2009 - 12/4/2009
Zone D: 12/7/2009 - 1/15/2010
Zone C: 1/18/2010 - 2/05/2010
Zone B: 2/8/2010 - 2/28/2010
Zone A: 3/1/2010 - 3/12/2010

 


During these flushing activities, local traffic may have to be diverted in accordance with the Department of Transportation or Tampa’s Traffic Engineering Division’s approved detour routing. We strive to make the detour period as short as possible. Also, regardless of safety procedures used, construction sites are very dangerous. Please keep children and pets away from all construction and flushing sites at all times.

We appreciate your patience and understanding, and thank you for your cooperation. If you have any questions concerning the construction of this project, please contact the Tampa Water Department's Reclaimed Water and Continuous Improvement Manager, Sandra Anderson at (813) 323-5303 or the Reclaimed Water Section online through the Customer Service Center.
 


Copyright © 1996-2009 City of Tampa.  All rights reserved. - Last Updated: 11/13/2009