Temporary Lane Closures N 46th Street to begin on August 31, 2020, for Utility Construction

Posted
08/31/20
This notice is archived content and this information may no longer be accurate.

A portion of N 46th St between Busch and Linebaugh will be closed daily from 9 am to 4 pm beginning on Monday, August 31, 2020 for utility construction, to be extended.  A private contractor will be installing water main on the west side of N 46th Street between E Busch Boulevard and E Linebaugh Ave.  The work will be completed in seven (7) phases.

 

Phase 1, N 46th Street between E 97th Ave and E 98th Ave will have a southbound lane closure at 9 AM on August 31, 2020.  Southbound through traffic will be detoured to E Bougainvillea Ave to McKinley Dr to E Busch Boulevard.  N 46th Street southbound between E 97th Avenue and E 98th Avenue is scheduled to be open on Friday, September 11, weather permitting.  Phase 2 will begin immediately following the completion of phase 1 construction.

 

During phase 2, N 46th Street southbound between E 98th Avenue and E 99th Avenue will close.  Southbound through traffic will be detoured to E Bougainvillea Ave to McKinley Dr to E Busch Boulevard.  Phase 3 will begin immediately following the completion of phase 2 construction.

 

During phase 3, N 46th Street southbound between E 99th Avenue and E Linebaugh Avenue will close.  Southbound through traffic will be detoured to E Bougainvillea Ave to McKinley Dr to E Busch Boulevard.  Phase 4 will begin immediately following the completion of phase 3 construction.

 

During phase 4, E Linebaugh Avenue will be closed west of N 46th Street.  Traffic will be detoured  to Mckinley Drive and E Busch Boulevard to N 46th St.  Phase 5 will begin immediately following the completion of phase 4 construction.

 

During phase 5, N 46th Street will be closed north of E Linebaugh Avenue.  Traffic will be detoured from E Bougainvillea Ave to Mckinley Drive to E Busch Boulevard.  Phase 6 will begin immediately following the completion of phase 5 construction.

 

During phase 6, a sidewalk closure will be required on the west side of N 46th Street between E Busch Boulevard to E Eva Street.  Phase 7 will begin immediately following the completion of phase 5 construction.

 

During phase 7, N 46th Street southbound between E Eva Street and E Wilma Street will close.  Southbound through traffic will be detoured to E Bougainvillea Ave to McKinley Drive to E Busch Boulevard.

 

Sidewalks in the work areas will be closed during the construction.  Pedestrians will be detoured to other available sidewalks with signage.

 

All lanes on N 46th Street between E Busch Boulevard and E Linebaugh Ave will reopen to traffic by 4 PM on Friday, October 30, 2020