Temporary Road Closure Channelside Drive to begin February 16, 2020 for Utility Construction

Posted
02/10/20

A portion of Channelside Drive between S Jefferson Street and Water Street (formerly Old Water Street) will close at 9 am beginning on Sunday, February 16, 2020 for utility construction. A private contractor will be installing a valve on a chiller line on the north side of Channelside Drive between Water Street and S Nebraska Avenue. 

Both eastbound lanes on Channelside Drive between S Jefferson Street and Water Street and one (1) eastbound lane on Channelside Drive between S Florida Avenue and S Jefferson Street will close at 9 am on February 16, 2020.

Two (2) eastbound lanes on Channelside Drive between S Florida Avenue and S Jefferson Street will be maintained at all times during construction, with delays.

Two (2) westbound lanes on Channelside Drive between Water Street and S Nebraska Avenue will be maintained on the south side of Channelside Drive at all times during construction, with delays.

All lanes on Channelside Drive will be open to traffic by 4 pm on Tuesday, February 25, 2020, weather permitting.

The City recommends using alternate routes to avoid traffic congestion.

Road Closure

ROW-20-0000822

See all road closures at www.tampagov.net/RoadClosures

For additional information, please contact:

Debbie Herrington, P.E., Right of Way Management

City of Tampa Planning & Development Department

(813) 274-3100, Option 5; catherine.coyle@tampagov.net